NEW QUESTION 104
Match each activity (on the left) to its definition (on the right).
Answer:
Explanation:
NEW QUESTION 105
In a Lean Software Development environment, the Project Leader strives to eliminate:
- A. Defects and features with low value stream values.
- B. Work in Process (WIP) and bugs.
- C. Delays and building what is not needed.
- D. Poor requirements and changing scope.
Answer: A
NEW QUESTION 106
A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint.
What should the team do?
- A. Work extra hours to complete the story and satisfy the customer's requirements.
- B. Advise the product owner that the story will have to wait until the next sprint.
- C. Increase the length of the sprint to accommodate the story.
- D. Break down the story into smaller increments and negotiate other stories on the sprint backlog.
Answer: D
NEW QUESTION 107
A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities.
What should the agile project manager do?
- A. Request the project teams' questions in writing prior to the next meeting
- B. Facilitate a meeting with each team and the product owner to find a solution
- C. Provide both teams with each project's documentation
- D. Provide both project teams with the highest priority needs
Answer: B
Explanation:
Explanation
NEW QUESTION 108
In Agile projects, the technique in which planning is done at three distinct horizons is known as:
- A. Monte Carlo Analysis.
- B. Portfolio Management.
- C. DelphiTechnique.
- D. Progressive Elaboration.
Answer: D
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION 109
Affinity Estimating is a technique many teams use to quickly and easily estimate a large number of user stories. What should be the minimum size for the items in the Product Backlog?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: A
NEW QUESTION 110
Two similar stories, A and B, are estimated at 3 story points. Story C, is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.
What should the agile practitioner do?
- A. Assign more resources to story B to bring it in line with the estimate
- B. Reestimate all stories including values for A, B and C
- C. Assign story B more than 8 story points so to provide a better estimate
- D. Add points to story B's iteration to account for the error but keep story B at 3 points
Answer: A
NEW QUESTION 111
Drag and Drop Question
While managing the Agile Product Lifecycle, Match the frequency with which you update the five Agile plans.
Answer:
Explanation:
NEW QUESTION 112
Kanban cards should always be written using User Stories.
- A. False
- B. True
Answer: A
NEW QUESTION 113
A value stream map is a tool used to identify the:
- A. Most likely flow of project risks.
- B. Waste across the entire process.
- C. Most valuable team interactions.
- D. Highest value product features.
Answer: B
NEW QUESTION 114
How do you best describe the primary role of an Agile leader?
- A. Manage stakeholders
- B. Manage teams without managing their tasks
- C. Manage WBS, schedule and cost of project
- D. Manage work allocation to team members
Answer: B
NEW QUESTION 115
Agile Teams use Planning Poker for estimation. Which of the following is NOT true about Planning Poker?
- A. The highest estimate is considered the final estimate
- B. It combines expert opinion, analogy, and disaggregation into an enjoyable approach to estimating that results in quick but reliable estimates.
- C. The team for Planning Poker should not exceed more than 10 participants
- D. Participants include all of the developers on the team
Answer: A
NEW QUESTION 116
A common reason that a story may not be estimable is that the:
- A. business needs are prioritized over the system design.
- B. developers do not understand the tasks related to the story.
- C. team has no experience in estimating.
- D. team lacks domain knowledge.
Answer: D
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION 117
Extreme Programming (XP) defines four basic activities that are performed during the software development process. These include designing, coding, testing and ...?
- A. Listening
- B. Leveling
- C. Communicating
- D. Collaborating
Answer: A
NEW QUESTION 118
Which of the following is NOT a characteristic of Agile project manager?
- A. Manages daily tasks of the team members
- B. Facilitates collaboration
- C. Assumes different leadership styles for different stages of team formation
- D. Allows team to self-manage
Answer: A
NEW QUESTION 119
Pick 5 activities that are the responsibilities of the development team in Scrum.
Answer:
Explanation:
NEW QUESTION 120
Based on the burndown chart, what is the iteration's status?
- A. It look more time than expected and had to be lengthened
- B. It trended behind schedule and did not complete everything on time
- C. It trended ahead of schedule and completed everything on time
- D. It took less time than expected and had to be shorted
Answer: A
NEW QUESTION 121
What do project reports show during the Sprint review meeting?
- A. Earned value measurement (EVM)
- B. Return on investment (ROI)
- C. Actual results to the plan
- D. Estimates compared to the baseline
Answer: B
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION 122
An organization adopts Agile practices and implements an incremental delivery strategy. If implemented correctly, the company should recognize improved:
- A. project cost management by making incremental payments on contracts.
- B. procurement processes by requiring vendors to ship materials as needed.
- C. project Return on Investment (ROI) by releasing individual features to market.
- D. customer satisfaction by specifying project shipping dates in the contract.
Answer: C
NEW QUESTION 123
A seven-member agile team's composition vanes considerably in age, gender culture, personality type and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?
- A. Networking
- B. Leadership
- C. Social awareness
- D. Communication
Answer: C
NEW QUESTION 124
......