NEW QUESTION 43
A test organization is trying to implement an improvement goal to develop a quantitative understanding of product quality, as part of the process area Product Quality Evaluation.
Which of the following specific practices needs to be addressed as part of process area 4.2 (Product Quality Evaluation) specific goal 1 Project Goals for Product Quality and their Priorities are Established?

  • A. Identify non-functional product risks
  • B. Measure product quality quantitatively throughout the lifecycle
  • C. Establish test process measures
  • D. Identify product quality needs

Answer: D

 

NEW QUESTION 44
Which of the following are valid reasons to perform a TMMi assessment?
1. Evaluate the performance of testers
2. Find areas to need to be improved
3. Determine which accomplishments have been made
4. As a basis to become formally TMMi certified

  • A. 1, 3 and 4
  • B. 2, 3 and 4
  • C. 1, 2 and 4
  • D. 1, 2 and 3

Answer: B

 

NEW QUESTION 45
Which of the following statements is FALSE about the level 5 process area Defect Prevention?

  • A. Action proposals drive the improvement activities to prevent defects from reoccurring.
  • B. Defect prevention practices propose solutions to eliminate common causes of defects.
  • C. In order to prevent as many defects as possible, all defects should be analyzed.
  • D. Defect Prevention is based on an analysis of a subset of all defects.

Answer: C

 

NEW QUESTION 46
Which generic practice addresses tailoring a managed process from the organization's set of standard processes?

  • A. Monitor and control the process
  • B. Objectively evaluate adherence
  • C. Establish a defined process
  • D. Establish an organizational policy

Answer: C

 

NEW QUESTION 47
Study the following description:
"Testing is a thoroughly defined, well-founded and measurable process. Testing is perceived as evaluation; it consists of all lifecycle activities concerned with checking products and related work products." To which TMMi maturity level does this description apply?

  • A. TMMi Level 5 Optimization
  • B. TMMi Level 2 Managed
  • C. TMMi Level 4 Measured
  • D. TMMi Level 3 Defined

Answer: C

 

NEW QUESTION 48
A test process assessment has been performed at an embedded software organization. All process areas at TMMi Levels 2 and 3 were in scope of the assessment. Many practices required by the TMMi model are already in place, but the organization is missing a master test plan spanning multiple test levels.
Which of the following process areas would most likely need specific attention to address the above-mentioned shortcoming?

  • A. Test Life Cycle and Integration
  • B. Test Planning
  • C. Test Policy and Strategy
  • D. Test Organization

Answer: A

 

NEW QUESTION 49
Consider the following characteristics of an assessment:
* the assessment is performed by an accredited TMMi assessor.
* only interviews are used as evidence.
To which type of assessment do these characteristics relate?

  • A. Informal assessments
  • B. Both formal and informal assessments
  • C. Formal assessments
  • D. Neither formal nor informal assessments based on TAMAR

Answer: A

 

NEW QUESTION 50
Which of the following statements is NOT a typical business reason for test improvement?

  • A. Reduce time to market by increasing efficiency of testing activities.
  • B. Introduce a new process improvement framework.
  • C. Reduce the costs of failure by improving effectiveness of testing.
  • D. Increase predictability of testing.

Answer: B

 

NEW QUESTION 51
Improvement models can have a staged and/or continuous representation. The TMMi has been developed as a staged model.
Which of the following statements regarding a staged improvement model is TRUE?

  • A. Practical experiences have shown that a staged representation is more difficult to use than a continuous representation due to its flexibility.
  • B. A staged representation has no fixed set of levels to proceed through.
  • C. A staged representation uses a predefined set of process areas to define an improvement path for an organization.
  • D. An organization can select process areas for improvement based on business objectives.

Answer: C

 

NEW QUESTION 52
Which of the following is a critical success factor that is typically most relevant while establishing improvements?

  • A. Organize test improvement as a project
  • B. The maturity of the development organization
  • C. Management commitment
  • D. Work on both long term and short term goals

Answer: D

 

NEW QUESTION 53
Which TMMi level 3 process area includes the specific practice Establish the Organization's Test Process Database"?

  • A. Test Training Program
  • B. Peer Review
  • C. Test Lifecycle and Integration
  • D. Test Organization

Answer: C

 

NEW QUESTION 54
Which of the following statements best describes the difference between a Specific Goal and a Generic Goal in the TMMi model?

  • A. A Specific Goal is the institutionalization of a Generic Goal.
  • B. A Generic Goal is applicable to multiple process areas, whereas a Specific Goal is applicable to one process area only.
  • C. Generic Goals are re-used from the CMMI and the Specific Goals are related to their implementation specifically for testing.
  • D. A Specific Goal is applicable to multiple process areas, whereas a Generic Goal is applicable to one process area only.

Answer: B

 

NEW QUESTION 55
Which type of TMMi model component is described hereafter?
"The components guide those who implement improvements or perform assessments. Either the practices as described or acceptable alternatives to the practices must be present in the processes of the organization before goals can be considered satisfied."

  • A. Alternative component
  • B. Required component
  • C. Expected components
  • D. Informative components

Answer: C

 

NEW QUESTION 56
What is an example of an indirect benefit for a test improvement program?

  • A. Higher levels of defect detection
  • B. Shortened lead-time of test execution phase
  • C. Improved (more reliable. test estimations
  • D. Improvement in staff motivation

Answer: D

 

NEW QUESTION 57
Which of the following are NOT specific goals of the TMMi level 5 process area Test Process Optimization?
1. Select test process improvements
2. Determine, plan and implement test process improvements
3. Evaluate New Testing Technologies to Determine their Impact on the Testing Process
4. Deploy test process improvements
5. Monitor product quality against plan and expectations

  • A. 2 and 5
  • B. 1 and 4
  • C. 2 and 3
  • D. 3 and 5

Answer: A

 

NEW QUESTION 58
TMMi distinguishes between required, expected and informative components.
Which of the following is an example of an informative TMMi model component?

  • A. Generic Practices
  • B. Sub-practices
  • C. Generic Goals
  • D. Specific Practices

Answer: B

 

NEW QUESTION 59
An organization already at TMMi level 4 is now trying to also achieve TMMi level 5 compliance.
Which of the following process areas is within the scope of this specific test improvement programme?

  • A. Quality Control
  • B. Advanced Reviews
  • C. Test Measurement
  • D. Product Quality Evaluation

Answer: A

 

NEW QUESTION 60
Your organization performs code reviews and architectural reviews on a regular basis, in order to measure product quality early in the lifecycle.
This is an example of implementation of a specific practice from which TMMi level 4 process area?

  • A. Quality Control
  • B. Test Measurement
  • C. Product Quality Evaluation
  • D. Advanced Reviews

Answer: D

 

NEW QUESTION 61
Which of the following is a typical element of a test policy?

  • A. Test types to be carried out at each level
  • B. The quality levels to be achieved
  • C. Approach to regression testing
  • D. Define product risks categories

Answer: B

 

NEW QUESTION 62
Which of the following activities is one that will typically be performed as part of the Diagnosing phase of the IDEAL test improvement cycle?

  • A. Plan Actions
  • B. Develop Recommendations
  • C. Develop Solution
  • D. Develop Approach

Answer: B

 