Try CTFL-2018 Free Now! Real Exam Question Answers Updated [Aug 11, 2023]
Get Ready to Pass the CTFL-2018 exam with ISTQB Latest Practice Exam
NEW QUESTION # 24
Tests have been specified for the latest software release and users have prioritised these.
However, there are some dependencies between tests as shown in the table below (e.g. Test ID. '123' cannot be run until Test ID. '456' has been successfully completed).
Which test execution schedule best meets the prioritisation and dependency conditions?
- A. 3, 5, 7, 10, 2, 4, 6, 8, 9, 1.
- B. 5, 7, 4, 3, 9, 10, 1, 6, 8, 2.
- C. 6, 1, 2, 9, 4, 3, 5, 7, 8, 10.
- D. 1, 4, 3, 5, 2, 7, 9, 10, 6, 8.
Answer: D
NEW QUESTION # 25
Given the following decision tables, what is the expected result for the test case listed below?
Test Case: Purchase a Toaster weighing 9kg for £10.
- A. No need to pay in cash, free delivery.
- B. Must pay in cash, no free delivery.
- C. Must pay in cash, free delivery.
- D. No need to pay in cash, no free delivery.
Answer: D
NEW QUESTION # 26
Which of the following would achieve the HIGHEST level of testing independence for a project's system test level?
- A. Training developers to design good tests for the test team to execute.
- B. Minimising contact between testers and developers during test design to avoid bias.
- C. Outsourcing test design and execution to a different company.
- D. Having the company's independent test team design and execute the tests.
Answer: A
NEW QUESTION # 27
Which of the following are triggers for Maintenance testing?
a) System migration from one platform to another.
b) Retirement of a system.
c) Preparation for an audit of a system.
d) Modifications to a system.
e) Development of a whole new system.
- A. a, c and d.
- B. a, d and e.
- C. b, c and e.
- D. a, b and d.
Answer: A
NEW QUESTION # 28
Which of the following is an approach that can be used for exploratory testing?
- A. A tester methodically executes tests from a list of possible failures, based on experience, defect and failure data.
- B. A tester analyses, designs and implements tests based on external rules and standards.
- C. Tests are designed based on the guidance of stakeholders and experts outside the test team.
- D. Time-boxed test sessions are created, during which a tester uses a test charter containing test objectives to guide the testing.
Answer: C
NEW QUESTION # 29
Testing effort can depend on a number of factors, which one of the following is MOST likely to impact the amount of effort required?
- A. The planned use of a project management tool to schedule tasks.
- B. The ratio of developers to testers in the project team.
- C. The responsibilities for testers and developers being clearly defined.
- D. The predicted number of defects and the amount of rework required.
Answer: A
NEW QUESTION # 30
Which of the following are benefits of an independent test team, and which are drawbacks?
a) Independent testers can find different defects.
b) Developers may put less emphasis on quality.
c) Independent testers can be seen as the reason for delayed projects.
d) Independent testers can verify assumptions made during the specification of a system.
- A. a and d are benefits, b and c are drawbacks.
- B. c and d are benefits, a and b are drawbacks.
- C. b and c are benefits, a and d are drawbacks.
- D. a and b are benefits, c and d are drawbacks.
Answer: A
NEW QUESTION # 31
A student needs to score at least 50 points to pass. If they score at least 100 points they will achieve a merit and if they score at least 150 points they will achieve a distinction.
Which two values are in the same partition?
- A. 55 and 120.
- B. 45 and 55.
- C. 50 and 60.
- D. 45 and 170.
Answer: C
NEW QUESTION # 32
Which of the following BEST describes how configuration management supports the test process?
- A. It enables incidents to be tracked from discovery and classification to correction and confirmation of the solution.
- B. It helps the test manager to decide how best to integrate and coordinate the testing activities into the software life cycle.
- C. It enables the tester to reproduce the tested item through unique identification and version control.
- D. It enables the tester to systematically design test conditions, cases and data.
Answer: C
NEW QUESTION # 33
Which of the following is a key difference between black box and white box test design techniques?
- A. Black box techniques use software code to derive test cases, white box techniques do not.
- B. White box techniques can measure the extent of code coverage, black box techniques can not.
- C. White box techniques derive test cases from models of the software, black box techniques do not.
- D. White box techniques use functional design specifications to derive test cases, black box techniques do not.
Answer: B
NEW QUESTION # 34
A holiday club restricts those booking the holiday, to people between the ages of 18 and 30 inclusive.
Using three-point boundary values, what ages would be required to test the lower and upper boundary?
- A. 17, 18, 19, 29, 30, 31.
- B. 17, 18, 19, 30, 31, 32.
- C. 18, 19, 20, 28, 29, 30.
- D. 16, 17, 18, 30, 31, 32.
Answer: A
NEW QUESTION # 35
An issue has been found in a production system, where a code component fails to release memory after it has finished using it. Which of the following tools would have been the MOST effective at detecting this defect during Performance testing?
- A. Dynamic analysis tool.
- B. Test Execution tool.
- C. Configuration management tool.
- D. Coverage measurement tool.
Answer: A
NEW QUESTION # 36
Given the following state transition diagram where SS is the start state:
Which of the following answers describes a test case that only uses valid transitions to exercise all states, using the minimum number of transitions?
- A. SS-S1-S2-S3.
- B. SS-S3-S2-S1.
- C. SS-S1-S3-S2.
- D. SS-S3-SS-S1-S3-S2.
Answer: C
NEW QUESTION # 37
Testing and Debugging are key activities in the software development lifecycle.
Which of the following are DEBUGGING activities?
a) Designing tests to find failures.
b) Locating the cause of failures.
c) Analysing and fixing the defects.
d) Executing tests to show failures.
- A. c and d.
- B. b and c.
- C. a and d.
- D. a and b.
Answer: D
NEW QUESTION # 38
Which of the following options describe the chain of events in the correct sequence?
- A. Fault, bug, mistake.
- B. Failure, bug, error.
- C. Error, fault, failure.
- D. Mistake, failure, fault.
Answer: C
NEW QUESTION # 39
......
Pass Your Next CTFL-2018 Certification Exam Easily & Hassle Free: https://www.itexamdownload.com/CTFL-2018-valid-questions.html
Get Prepared for Your CTFL-2018 Exam With Actual ISTQB Study Guide!: https://drive.google.com/open?id=149S5AcqArTzataAIKumpuXhqho6uyxCn